Due to SGS's experience in power generation and in desulphurization projects, the Hitachi-Cobra Consortium assigned SGS Portugal to manage and supervise all quality-related activities during the whole upgrade process of the Sines Thermal Power Plan

The main environmental impact caused by the combustion of fossil fuels in thermal power plants is the emission of carbon dioxide (CO2), sulfur dioxide (SO2), nitrogen oxide (NOx) and particles. In the fight against climate change, energy production plants represent a great potential to reduce green house gas (GHG) emissions.

In May 2006, a Desulphurization Project with the objective of reducing SO2 in the Sines Thermal Power Plant was launched by Energias de Portugal (EDP), one of Europe's major electricity operators.

Flue Gas Desulphurization (FGD) is a catalytic chemical process widely used to remove sulfur from natural gas and refined petroleum products. The aim of removing the sulfur is to reduce the sulfur dioxide emissions that result from using fuels in gas or oil burning power plants.

A consortium between Hitachi Ltd. and Cobra Instalaciones y Servicios, S.A., the main subcontractor for this project, was responsible for the turnkey solution for the desulphurization plant engineering, design, construction and implementation, as well as for the initial operations.

The project consisted of four units, one in each of the concerned production groups. The desulphurization facility was installed in the pieces where SO2 neutralization occurs, as well as in absorbers and in the preparation and storage facilities for plaster.

Due to SGS's experience in power generation and in similar desulphurization projects, the Hitachi-Cobra Consortium assigned SGS Portugal to manage and supervise all quality-related activities during the whole upgrade process. SGS proved to have competent, highly experienced professionals, thus enabling smooth workflow in the most critical and complex stages of the development.

SGS paid particular attention to the continuous availability of dedicated technical staff for the evaluation of technical conformity with engineering specifications of both materials and equipment used during the entire project.

Throughout the evaluation of technical conformity, continuous quality supervision was implemented during the production of in-line equipment, filters, instrumentation, pipes and plates for several tank assemblies onsite. The quality supervision by SGS aims to avoid failures in future operation caused by poor material quality or wrong choice of material. It also ensured that performance tests of the equipment on manufacturers' premises were carried out before delivery to the plant site.

Moreover, the SGS team onsite assured conformity with engineering specifications during project execution. Activities involved among others, Mechanical Testing, Non-Destructive Testing, Pressure Equipment Certification, Equipment Licensing and CE Marking. SGS services during assembling and instrumentation, electrical and automation activities focused on reviewing the subcontractors' specifications, evaluating their conformity with requirements, monitoring the tests, testing the welds, and final commissioning.

SGS also provided the Consortium with an entire support team whose job was to calculate and verify equipment and structures under different circumstances of the project assumptions or before changing specifications onsite. The team also assisted in finding proper materials and welding solutions and elaborating corrosion and anti-corrosion plans. In addition, SGS consulted with the competent official authorities and handled all details related to licensing.

The SGS team provided real time information and participated proactively in resolving any problems. Project Director Alejandro Suárez Serrats concluded saying: "The collaboration between the Hitachi-Cobra Consortium and SGS came through without any problems. Generally, the Consortium was very pleased with SGS, especially with the importance they gave to quality in this project."

SGS Industrial Services is one of the biggest business lines of the SGS Group, a global service provider for technical verification, inspection, testing and conformity assessment, ensuring that the customer's installations, materials, equipment, facilities and projects meet all quality and performance requirements, whether they are regulatory-, voluntary- or customer-based.

Share:


Tags: CE marking, climate change, Energias de Portugal, FGD, Flue Gas Desulphurisation, green house gas emissions, Mechanical Testing, NDT, Non-destructive Testing, power generation, Power Plants, quality control, SGS, thermal power plant


About SGS Portugal - Sociedade Geral de Superintendencia SA

View Website

Jose Fabiao
Press Contact, SGS Portugal - Sociedade Geral de Superintendencia SA
SGS Portugal - Sociedade Geral de Superintendencia SA
Pólo Tecnológico de Lisboa,
6 - Pisos 0 e 1
1600-546 L